LPG infrastructure / 5 min read

Kenya LPG reticulation permits: what housing developers need to prepare

EPRA’s May 2025 guidance and construction-permit checklist give residential project teams a clear starting point for coordinated LPG design and approvals.

Engineers review architectural plans and LPG pipe routes for a Kenyan residential development
7 October 20265 min readAll insights

EPRA’s May 2025 guidance and construction-permit checklist give residential project teams a clear starting point for coordinated LPG design and approvals.

Article

What EPRA’s May 2025 guidance covers

EPRA’s Guidelines on Licensing of LPG Reticulation were issued in May 2025. They cover the installation, supply, and sale of LPG through reticulated systems at domestic, commercial, and industrial premises where an individual storage tank has a water capacity above 150 litres.1 The guidance addresses engineering, safe installation, testing, commissioning, maintenance, and the licensing steps for these systems.

For a qualifying project, the guidelines say the proponent needs a construction permit to install the system and an operational licence before it is put into service.1 This is not a direction that every new housing development must adopt LPG reticulation. It is guidance for projects that are developing a reticulated LPG system, alongside applicable laws, standards, and county approvals.1

What the construction-permit package asks for

EPRA / Construction permit

Document brief  02

Submission set

EPRA’s construction-permit checklist calls for

  • coordinated architectural, electrical, mechanical, and civil engineering drawings,
  • as well as development permission,
  • a valid NEMA EIA licence,
  • and a fire-suppression design supported by calculations.2

Drawing coordination

What the plans need to show

Architectural drawings
The architectural drawings should show where LPG will be piped and the available gas ducts;
Electrical drawings
the electrical drawings should show electrical services in relation to those ducts.2

Mechanical drawings

The mechanical engineer’s drawings are especially important.

EPRA asks them to

  • specify installation materials and design limits;
  • include a Piping and Instrumentation Diagram (P&ID);
  • show the Pressure Regulation System (PRS) and its salient accident-prevention features;
  • locate and specify meters;
  • describe corrosion protection;
  • and identify the design standards and codes used.2

Make pressure control and safety visible early

A permit reviewer needs to see how the proposed system will control pressure and manage foreseeable risks. EPRA’s guidance describes first-stage regulation close to storage, further pressure reduction where the building arrangement calls for it, and final reduction at the meter before gas reaches an appliance. It also discusses regulator location and over-pressure and under-pressure shut-off protection.1 The project engineer should document the actual design basis and selected equipment rather than treating one arrangement as suitable for every building.

Coordinate the PRS with demand, pipe routes, meter locations, access for inspection, and the project’s fire-safety design. EPRA’s checklist separately asks for civil drawings showing works such as tank saddles, drainage, fencing, and hard-standing surfaces, and a fire-suppression design with its calculation basis.1, 2

Cabinet memo report: proposal, not permit rule

People Daily reported that a Cabinet memo proposed a framework requiring all housing developments, including affordable-housing projects, to provide for LPG reticulation as a prerequisite for approval.3 The article describes this as part of proposed regulations. Treat the reported measure as a proposal, not an in-force requirement, unless and until a formal law, regulation, Gazette notice, or current permit condition confirms its adoption.

If adopted as reported, developers could need to account for LPG reticulation earlier in site planning, building-services coordination, project budgets, and approval schedules. Homeowners and buyers could find their homes designed for a shared piped-gas system rather than individual cylinders, while housing associations and building managers would need a clear arrangement for system ownership, supply, maintenance, safety checks, and billing. These are possible planning implications, not confirmed terms of the proposal; the report does not specify who would operate the systems or how costs and responsibilities would be allocated.

EPRA’s May 2025 guidance sets out licensing and construction-permit requirements for qualifying reticulated systems; it does not itself establish a universal requirement for every housing development to install one.1 Before design freeze, confirm the current EPRA requirements, county permissions, standards, and project-specific approval conditions with the responsible professionals and authorities.1, 2

The practical takeaway

For developers and homeowners: if a project will use reticulated LPG, confirm current EPRA and county requirements, coordinate the permit drawings and safety plan early, and check that installation matches approved documents. The reported Cabinet memo is a proposal, not a universal rule in force. Our team can cross-check the installation checklist as a second set of eyes to help catch omissions; required approvals and professional sign-off still apply. That is the Continental Experts way.

References

Sources and further reading

  1. Energy and Petroleum Regulatory Authority (EPRA), Kenya. Guidelines on Licensing of LPG Reticulation (May 2025). View source
  2. Energy and Petroleum Regulatory Authority (EPRA), Kenya. Requirements for LPG Reticulation System Construction Permit. View source
  3. People Daily. Kenya’s ambitious plan to overhaul LPG sector. View source